The MetalSkin MMOL and SurgeMaster system extended the 13 3/8-in. casing string by 2,375 ft (724 m). This enabled the 11 3/4-in. long string to isolate the primary reservoir and reach a deeper, newly discovered production horizon.
The operation enabled immediate additional production without installing new production facilities.
The MMOL enabled through-drilling, tubular-running, and cementing operations while maintaining the desired 7 5/8-in. completion diameter.
The SurgeMaster system reduced surge pressures and protected the formation while running the tie-back shoe, MMOL, and long string.